JV Driver served as general contractor for Weyerhaeuser’s Grande Prairie Optimization Project. The program combined environmental and production-efficiency objectives through changes to chemical recovery, fibreline and machine-room systems. Construction included a two-stage oxygen-delignification system with washing, recausticizing modernization, washer and pump upgrades, a new chip bin and modifications to the pulp machine.

Scope of work

  • Oxygen delignification and pre- and post-oxygen washing
  • Recausticizing and polysulphide-system installation
  • Brownstock washers, press equipment and pump upgrades
  • Chip-bin replacement, pulp-machine upgrades and control room

RELATED ASSIGNMENTS

Mill modernization and process upgrades.

Browse this segment

LET’S GET TO WORK

Bring us your next challenge.

Tell us what you need to build, improve or maintain.

Discuss your project