Northern Saskatchewan
The assignment
JV Driver led the English River Constructors joint venture in delivering Cameco’s uranium slurry loadout facility at McArthur River. The facility included Pachuca tanks and a concrete containment wall approximately 100 feet high. The assignment brought civil, mechanical, structural, electrical and instrumentation work together in a northern construction environment.
Scope of work
- Slurry loadout facility construction
- Process tanks and concrete containment
- Civil, structural and mechanical installation
- Electrical and instrumentation services
Delivery experience
The profile records completion in eleven months through winter conditions and a peak workforce of 247 people. It reports no lost-time accidents for that assignment. The experience demonstrates the importance of labour planning and coordinated disciplines in a remote setting.