Belle Plaine Expansion
Location: Belle Plaine, SK
Client: Mosaic
JV Driver was awarded the Phase 1 Expansion to the Belle Plaine facility. The primary purpose of the expansion is to increase the water availability to the mine field in order to allow further solution mining. The award included the following scope:
- Two Salt Water Disposal Wells. Our scope is the piling, civil, piping, mechanical, electrical, instrumentation and cladding
- One Reclaim Brine Pump House. Our scope is the piling, civil, piping, mechanical, electrical, instrumentation and cladding
- Power House, including the setting of a package boiler. Our scope is the piling, civil, piping, mechanical, electrical, instrumentation and cladding
- Process Water Building. This building includes two tanks, one a raw water storage tank and the other, the hot water storage tank. Our scope is the piling, civil, piping, mechanical, electrical, instrumentation and cladding
- 138 KV Substation. Our scope is the piling, civil, structural steel, piping, mechanical, electrical, instrumentation and cladding.
In addition, to the construction scope of work we are providing constructability, purchasing and expediting services to our client.