Devon Jackfish

Location: Conklin, AB

Client: Devon

JV Driver completed the Jackfish project, a 35,000 barrel-per-day SAGD.

We were responsible for the entire scope of construction and self-performed all but the electrical and instrumentation. This work included all civil foundations and structural work required in the erection of the structures. In addition, JV Driver executed all work in the piping and mechanical scope, utilizing a 300 ton 2250 Manitowoc, with a maximizer, for the installation of modules and vessels from 100-250 tons. All rigging studies were conducted by JV Driver.

We utilized constructability reviews during the engineering phase to identify and implement cost effective solutions, including a patented form system, reducing costs and ensuring the project schedule.