Turbine and Generator
Location: Athabasca, AB
Client: Alberta Pacific Forest Ltd.
JV Driver completed the installation of a new 35 MW steam Turbine and Generator. This scope included the Civil, Rebar and Mechanical portion of work related to the installation of the Turbine and Generator at their mill near Athabasca, Alberta. The structure measures 6,850 square feet. JVD’s scope included piers and pier caps for the Turbine and Generator, floor slabs and installation of approximately 120 tons of rebar, as well as the installation of steam piping and an air condensing cooler and the installation of the generator and turbine. The project incorporated over 20,000 inches of pipe of varying commodities